Start Date: 2019End Date: 2019Status: CurrentProject DetailSector: TransportProject Activity Status: Progress to date is at 94% Project SummaryProject Promoter: Government of Zimbabwe Progress to date is at 94% for Bridge construction. Abutments and suspended slabs completed, parapet walls construction in progress. 4% completion for bridge approaches. Gravel stock piling in progress. Completion of the approaches is expected by end of April 2019. Accompanying Documents: Mt Darwin Rds .pdf