Start Date: 2019End Date: 2019Status: CurrentProject DetailSector: TransportProject Activity Status: Progress to date is at 63% Project SummaryProject promoter: Government of Zimbabwe Progress to date is at 63%. Surfacing, bases construction and culvert construction is underway.6km surfaced to date. Completion is expected by end of April 2019. Accompanying Documents: Mt Darwin Rds .pdf