Pembi Bridge construction and approaches

Start Date: 
2019
End Date: 
2019
Status: 
Current
Project Detail
Sector: 
Transport
Project Activity Status: 
Progress to date is at 94%
Project Summary

Project Promoter: Government of Zimbabwe

Progress to date is at 94% for Bridge construction. Abutments and suspended slabs completed, parapet walls construction in progress. 4% completion for bridge approaches. Gravel stock piling in progress. Completion of the approaches is expected by end of April 2019.