Mwenje Nyarumwe irrigation scheme – Chiweshe
Functional irrigation system to irrigate 97 hectares of land.
Functional irrigation system to irrigate 97 hectares of land.
The project scope entails the construction of a rockfill dam, covering a catchment area of 4500km2 and a full supply capacity of 260 000ML.
Project Promoter: Government of Zimbabwe
Progress to date is at 94% for Bridge construction. Abutments and suspended slabs completed, parapet walls construction in progress. 4% completion for bridge approaches. Gravel stock piling in progress. Completion of the approaches is expected by end of April 2019.
Project Promoter: Government of Zimbabwe
Progress to date is at 37%. Surfacing, bases construction and culvert construction is underway.1.8km surfaced to date. Completion is expected by end of April 2019.
Project promoter: Government of Zimbabwe
Progress to date is at 63%. Surfacing, bases construction and culvert construction is underway.6km surfaced to date. Completion is expected by end of April 2019.
Existing on-campus student facilities at BUSE are not adequate to meet the increase in the number of students enrolled at the institution.
5no. office multistorey blocks
Construction of halls of students residence
Construction of halls of students residence
Construction of halls of students residence